Palm County Sector-78

Palm County Sector-78

Sr.No

Work Description

 

Progress 

1

Main Entrance Gate  ( Design Revised )

 

0%

2

Sewer Line Work

 

95%

3

Storm Water Work

 

95%

4

Rain water Harvesting

 

100%

5

Sewarage Treatment Plant Work

 

80%

6

Under Ground Water Tank Work

 

70%

7

Water Supply Work

 

95%

8

Road Work  ( Design Revised )

 

50%

9

Electrical Sub-station

 

50%

10

Laying of Cables  ( Casing for cables )

 

90%

11

External Developments  ( Design Revised )

 

40%

 

 